Port Area and Complete Streets Infrastructure Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Status:

The Project is currently at 35% Design and is still pending environmental clearance. The Project will progress to 65% after approval of the next phase of the design contract  

Location:

Harbor Blvd from the US 50 On/Off ramp to Industrial Blvd; Industrial Blvd from Harbor Blvd to the Palamidessi Bridge; Lake Washington Blvd from the Palamidessi Bridge to Southport Parkway; Southport Parkway from Lake Washington Blvd to Promenade Street. 

 

Description or Scope:

The Port Area Infrastructure and Complete Streets Project will not only include road rehabilitation but will also incorporate complete streets elements, including utility upgrades, filling sidewalk gaps, and adding bike lanes to enhance safety and to meet the needs of pedestrians, bicyclists, motorists, and public transportation uses.   

Project Benefits:

Complete Streets projects are designed to enable safe use and efficient movement and are designed to meet the needs of pedestrians, bicyclists, motorists, and public transportation users. In addition, improving pavement conditions will enhance the safety of drivers. 

Tentative Schedule:

2025 2026 2027 2028 2029
Winter Spring Summer Fall Winter Spring Summer Fall Winter Spring Summer Fall Winter Spring Summer Fall Winter Spring Summer Fall
35 % Design
65% Design
Environmental Clearance
UPRR Coordination
Community Outreach
Final Design
Bidding
Construction

 

Cost(s):

 

Phase 1 Design - $569,600 

Phase 2 Design – To be determined (TBD) 

Estimated Construction Costs: (Not currently funded)  

  1. Harbor Blvd - $2,059,112 

  2. Industrial Blvd - $6,530,000 

  3. Lake Washington Blvd - $1,980,000 

  4. Southport Parkway - $21,980,000 

 

 

Funding:

 

Phase 1 Design 

Measure G - $1,000,000

SB1 - $500,000

Phase 2 Design 

Regional Surface Transportation Grant - $400,000

Construction Phase – TBD 

 

Consultant(s):  

 

Design Phase 1: Bennett Engineering  

 

Additional Resources:

 

 

Contact: 

 

Joanna Ortiz  

Assistant Engineer  

Capital Projects Department  

Joannao@5dexam.com 
  

 

Project Boundaries: 

 Project Boundaries

Proposed improvements:  

Exhibit 1 - Existing Cross Section for Harbor Blvd

Exhibit 1 - Existing Cross Section for Harbor Boulevard

Exhibit 2 - Proposed Cross Section for Harbor Blvd

Exhibit 2 - Proposed Cross Section for Harbor Boulevard

Exhibit 3 - Existing Cross Section for Industrial Blvd

Exhibit 3 - Existing Cross Section for Industrial Boulevard

Exhibit 4 - Proprosed Cross Section for Industrial Blvd

Exhibit 4 - Proposed Cross Section for Industrial Boulevard

Exhibit 5 - Existing Cross Section for Southport Parkway

Exhibit 5 - Existing Cross Section for Southport Parkway

 Exhibit 6 - Proprosed Cross Section for Southport Parkway

Exhibit 6 - Proposed Cross Section for Southport Parkway

 

Lasted Edited