City of West Sacramento
Home MenuPort Area and Complete Streets Infrastructure Project
Status:
The Project is currently at 35% Design and is still pending environmental clearance. The Project will progress to 65% after approval of the next phase of the design contract
Location:
Harbor Blvd from the US 50 On/Off ramp to Industrial Blvd; Industrial Blvd from Harbor Blvd to the Palamidessi Bridge; Lake Washington Blvd from the Palamidessi Bridge to Southport Parkway; Southport Parkway from Lake Washington Blvd to Promenade Street.
Description or Scope:
The Port Area Infrastructure and Complete Streets Project will not only include road rehabilitation but will also incorporate complete streets elements, including utility upgrades, filling sidewalk gaps, and adding bike lanes to enhance safety and to meet the needs of pedestrians, bicyclists, motorists, and public transportation uses.
Project Benefits:
Complete Streets projects are designed to enable safe use and efficient movement and are designed to meet the needs of pedestrians, bicyclists, motorists, and public transportation users. In addition, improving pavement conditions will enhance the safety of drivers.
Tentative Schedule:
2025 | 2026 | 2027 | 2028 | 2029 | ||||||||||||||||
Winter | Spring | Summer | Fall | Winter | Spring | Summer | Fall | Winter | Spring | Summer | Fall | Winter | Spring | Summer | Fall | Winter | Spring | Summer | Fall | |
35 % Design | ||||||||||||||||||||
65% Design | ||||||||||||||||||||
Environmental Clearance | ||||||||||||||||||||
UPRR Coordination | ||||||||||||||||||||
Community Outreach | ||||||||||||||||||||
Final Design | ||||||||||||||||||||
Bidding | ||||||||||||||||||||
Construction |
Cost(s):
Phase 1 Design - $569,600
Phase 2 Design – To be determined (TBD)
Estimated Construction Costs: (Not currently funded)
-
Harbor Blvd - $2,059,112
-
Industrial Blvd - $6,530,000
-
Lake Washington Blvd - $1,980,000
-
Southport Parkway - $21,980,000
Funding:
Phase 1 Design
Measure G - $1,000,000
SB1 - $500,000
Phase 2 Design
Regional Surface Transportation Grant - $400,000
Construction Phase – TBD
Consultant(s):
Design Phase 1: Bennett Engineering
Additional Resources:
Contact:
Joanna Ortiz
Assistant Engineer
Capital Projects Department
Joannao@5dexam.com
Project Boundaries:
Proposed improvements:
Exhibit 1 - Existing Cross Section for Harbor Boulevard
Exhibit 2 - Proposed Cross Section for Harbor Boulevard
Exhibit 3 - Existing Cross Section for Industrial Boulevard
Exhibit 4 - Proposed Cross Section for Industrial Boulevard
Exhibit 5 - Existing Cross Section for Southport Parkway
Exhibit 6 - Proposed Cross Section for Southport Parkway
Lasted Edited
10/23/2024